77 Fulham Palace Road site progress
Share your story:

Very good progress after just nearly 2 ½ weeks onsite with 95% of the East elevation stickwork already complete.

The glass was delivered yesterday, and the glazing is expected to start imminently on the East with a start on the South elevation programmed for the 17th May 2016.

The efficient installation method includes making up ladder frames out of the curtain walling profiles in our site compound, then hanging them from the monorail with a minifor powered travel trolley.

Scheduled for completion in October this year, with a rapid installation to close up all floor plates and release following trades.