Royal Holloway University Site Progress
Share your story:

Following completion of the composite insulated backing structure to the lower ground floor on the eastern block, we have now completed installation of the ceramic granite cladding panels.

Installation of Copper to the central block to commence this week to the western elevation and perimeter cladding to the incline screen.

Progress on all fronts of the eastern block east elevation 2nd floor terrace, as the terracotta baguettes are due for completion this week.