Over the last few days, significant progress has been made at roof level, with key installations completed via mobile crane. The team has successfully installed the pavilion steel frame alongside glazing works. With curved steel frames weighing approximately 1.3T and curved glass at 550kg, this was no small task!
Additionally, we’ve replaced several internal beaded window glass panels using the Libro 600 3D head/overhang beam—an intricate process, but executed smoothly. This gives us full confidence in the replacement strategy moving forward.
Well done to everyone involved and we look forward to project completion!