The installation of the copper cladding on the Eastern block is rapidly progressing. Within 2 weeks the East elevation is programmed to complete on the copper and aluminium cladding. The site team are also working hard to target the end of this month to have have the Eastern block watertight to release the internal fit out works for the library.
Looking ahead we will be commencing installation on the West elevation, the Central block perforated copper and the South elevation glazing.