Today has marked another milestone for the Wedge House scheme. We have finally commenced the installation of the first few aluminium windows into the precast panels up in Thorpe Precast’s factory in Stoke-on-Trent.
Across the rest of the project, Design is progressing well on all elements that are being constructed onsite and as we write, the concrete floor slabs are being poured which should see precast panels being able to be installed in approximately 4 months’ time.
Overall, a great project and we hope this method of construction will continue to grow.