Close
Lillie Square Site Progress
Share your story:

Block A installation is still in rapid progression, and nearing completion within the next few weeks. The last two blocks, G and H, are due to commence imminently once the pre-cast concrete has been installed.

Balcony installation has started on Block A and going well, with 22 installed and a further 30 to be installed during February with the remainder to follow.  The uniquely designed system is allowing completed modular units to be lifted to position once the façade is complete.

The project is currently on programme and set to finish on time.